PROJECT 009 · WHOLE HOME · 30 WEEKS
Center-hall colonial
A center-hall colonial with knob-and-tube wiring and closed-off rooms, renovated top to bottom while keeping the original staircase, trim and fireplace.
- Project no.
- 009
- Type
- Whole home
- Location
- Hartford, CT
- Duration
- 30 weeks
- Budget range
- $380k–$450k


Scope
- Full electrical and plumbing replacement
- Kitchen opened to the family room on a steel beam
- Original staircase, trim and oak floors restored
- Spray-foam insulation and new windows throughout
- Two bathrooms rebuilt and a third added upstairs
Timeline
30 weeks
- Wk 1–9Demo & rough-in
- Wk 10–22Build-out
- Wk 23–30Finishes & punch list
Budget
$380k–$450k
Final contract range, including permits, allowances and any signed change orders.